Schedule for Start of Shutdown 08

Ver March 11 2008 1730hrs

Wednesday March 12th

 

NOTE: Below to be executed as a soon as the RHIC run is declared over

 

 Time

Action

Personnel

End of RHIC run

(Between 0800 and 1400 hrs)

·        RHIC 8 and 10 o’clock to CA, all other RHIC to RA

·        CAS to PHENIX to aid in experimenter access (RA after plug opened)

·        10 O’clock to RA after HP survey

·        AtR Stays on NA

·        MCR/MSG

·        CAS

END of RHIC to 0400 Thursday

·        Studies in AGS. No Access Booster AGS U Upstream

 

 

 

Thursday March 13th

 

 Time

Action

Personnel

0400

·        Tandem switch from Au to Fe for NSRL

·        Tandem

0530:

·        Siemens Operator to LOTO MG set

·        Siemens

0600:

·        P. Rosas connects new filter for J10 bump for testing during the heat run

·        PSG

0800:

·        Siemens turns on set with heat run functions loaded

·        MCR/SW

1200:

·        CAS to apply CA LOTO to AGS

·        CAS

1300:

·        Pendzick et. al. CA access AGS for AtR measurement (AtR Q1 and Q2 on)

·        HP CA access for AGS Restricted Access Survey

·        ESF/MCR

·        HP

1400:

·        AGS opened for shutdown

·        Shutdown LOTO begins