Version November 4, 2009 P. Sampson
The table
below outlines Access Modes in the accelerator enclosures:
|
Accelerator
Access status key |
|
|
||||||||
|
No Access |
|
|
|
|||||||
|
Controlled Access |
|
|
|
|||||||
|
Restricted Access |
|
|
|
|||||||
|
|
|
|
|
|||||||
TTB Crossover
|
|
|
||||||||
|
LINAC |
LINAC to run starting Jan 1 |
|
||||||||
|
Booster |
|
|
||||||||
|
AGS |
|
|
|
|
||||||
|
AtR |
|
|
|
|
||||||
|
RHIC |
|
|
|
|
||||||
|
DATE |
|
Nov 12 |
Nov 16 |
Nov 23 |
Dec 2 |
Dec 4 |
|
|||
|
|
|
|||||||||
Useful links:
Follow the links below to view the timeline
for completion of many of the RHIC systems as they progress through this
shutdown
The
General View gives an overall summary of the present
situation
Items
in red may extend beyond the shutdown and be completed on Maintenance Days
|
Group |
Date Critical work is
complete |
Percent Complete |
Comments |
|
Mon 12/4/09 |
65% |
Awaiting
some parts for Stochastic, cooling vacuum and IPM. Awaiting
SC some component installation. Spin
Flipper work has begun. EBIS
Buncher install TBD |
|
|
Thu 12/4/09 |
65% |
Schedule
delayed awaiting some parts. Working
to finish on schedule |
|
|
Mon
12/01/09 |
75% |
Should
be on time. Critical path job is valve box renovation. Old
MMPS systems and hardware are available as fallback |
|
|
Tue
12/10/09 |
80% |
On
schedule. |
|
|
Fri
12/04/09 |
80% |
On
schedule |
|
|
Fri
12/04/09 |
55% |
Awaiting completion of assembly and
delivery components. |
|
|
Fri
12/04/09 |
80% |
On
schedule. |
|
|
Fri
12/01/09 |
80% |
Working
overtime on essential jobs, delays presently being reduced. Some delays
awaiting parts |



Power Supply Maintenance and Upgrades