Complex Schedule
Nov 18st-Nov 25th 2009
Ver 11/22/2009 pws
Current
Access modes:
|
Machine |
Access
Mode |
|
LINAC: |
RA |
|
Booster: |
NA |
|
NSRL: |
NA |
|
AGS: |
NA |
|
U, W, X,Y: |
NA |
|
RHIC : |
RA |
Schedule for Saturday, Sunday and Monday,
Nov 21-23 2009
|
Time and date |
Action |
Personnel |
|
Saturday (aZ) (After Zeno) |
·
Restricted Access LOTO applied to
the Booster ·
RA survey of Booster |
·
CAS ·
HP |
|
>0700hrs |
·
Booster to RA |
·
MCR |
|
1000hrs |
·
Booster to CA (Access continues) ·
Sweep and secure Booster |
·
MCR ·
CAS/MCR |
|
1100hrs |
·
Remove LOTO from Booster and
restore |
·
CAS/MCR |
|
1300hrs |
·
Resume setup with beam in AGS ·
Vacuum group to advise |
|
|
Monday 11/23 0700 |
·
Apply Controlled Access LOTO for
AGS |
·
CAS |
|
0800 |
·
Access AGS for RF work- North
conjunction area (Monday only) ·
Assess Booster Access needs |
·
MCR/CAS /HP/RF |
|
1200hrs |
·
Secure AGS, remove LOTO |
·
MCR/CAS |
|
1300hrs** |
·
Continue setup with beam** |
·
OPS** |
** Access to Booster depends on results of EBIS buncher leak repair, may
affect time of setup continuation **
Check for Job Approval, some jobs may need to be edited or may not be
allowed at this time
For a complete list of jobs see JOBS
For a time table Ring Access See Ring
Access
Ver Sunday, November 22, 2009 pws
Booster
startup went well- great work!
·
Begin
submission for “Maintenance Days” in Booster (after hours until Nov 23rd)
The
Booster is running for NSRL
·
Booster
setup with gold successful this week (Mon Night)
·
October
4th began RHIC scrub on schedule
·
L10
cavity commissioning and RF check out continues, with beam
·
AGS
equipment checkout continues
·
AGS
setup with beam continues
·
AtR items must be completed this week
o AtR berm to be
swept Thursday (today)
o RS LOTO must be removed from AGS
extraction and transport to the W dump
o RHIC RS LOTO box located in 911B rm.
222
·
Access
controls has begun testing in RHIC, some interruption early morning and
evenings- call MCR 5388 for problems with access
o At times alarms will ring- TV will
have a warning when ACS informs MSG
·
This
weekend:
o Access to Booster 0700-1100 Saturday
for EBIS buncher install prep work- see Schedule
o Monday, Tuesday (and Wednesday?),
Booster Access for EBIS bunches install/Bake preperation
·
Three
shifts with NO ACCESS to RHIC, 1600-2400 Nov 30, Dec 1, 2 for roll ups.
·
Vender
tests of EBIS dipole in January, time TBD.
Red
Letter Days for start up- Items in grey
are completed:
·
Nov
20rd – 23th :
o Beam to W dump, no access to AGS, U
line, W, X, Y lines.
o Daytime Access.
·
Dec
4th Blue injection
·
Dec
8th Yellow injection
· AGS Access November 9, 10, 11– AGS main Magnet repair and tune jump quads,
Completed
· Controls startup for AGS and RHIC is complete
· Siemens and Westinghouse MG sets ran (no load), some issues but ok- COmplete
· AGS BLMs energized for tests this week
· A15 MW checkout complete
· J7 mechanical installation complete
o
Modifications as access permits
this week.
· Last week in October:
o
Controls test of data flow will be
performed, some systems will be “Dry Run”(RMMPS ramp)
· October 31& Nov 1
o
Booster on restricted access for
wiring and barriered testing of EBIS dipoles
· Nov 02-03:
o
AGS systems turn on, Water, RF
etc…
o
Test Westinghouse- Heat run AGS
Main Magnets
o
Begin Systems checkout
o
Begin Live ACS testing in AGS
and AtR- Limited Access (eves?)
o
45K wave begins, ODH 0
classification in service bldgs and tunnels- observe
postings.
· Nov 05:
o
Dry run AGS with Siemens
o
RHIC at 45K
o
Begin ACS live testing in RHIC,
Access to be determined
o
Power supply work at RHIC begins
o
Tandem setup for gold begins
·
November 7-8th:
Vender testing of the EBIS dipoles in the Booster ring (Booster NA),
Rescheduled
· Today, L12 magnet installation am, pm Hi-pot
· Friday 11/13: Heat run and check-out AGS equipment.
· Final equipment checkout Friday 11/13, Mon 11/16 and Tues 11/17- NO AGS
ACCESS
· ACS critical device testing Friday and Monday- RS LOTO changes…
· Nov 16th:
o
Gold beam setup in Booster
begins after NSRL.
· Nov 17th:
o
Begin AGS setup with gold beam.
Eves after NSRL concludes.
Power outages for L1 and L2 substation need to be determined
as they will affect Booster/EBIS etc.