Cryogenic
System Cooldown Projection based on Full Compressor
Power Starting on February 2, 2009
.5
MW – Dec 8, 2008 through Jan 12, 2009 (temporary peaks up to 2 MW)
12/8/08 start cryo
plant scrub (9 days)
12/16/08 RHIC ring pressure testing complete,
insulating vacuum established
12/17/08 start scrub of RHIC ring (22
days)
2.5
MW – Jan. 9, 2009 through Feb 1, 2009
1/9/09 start 45K cooldown
of cryo plant (1 day)
1/10/09 start 45K wave in both RHIC
rings (23 days)
6
to 8 MW – February 2, 2009 through February 8, 2009
2/2/09 start 4K wave in Blue ring, Hi potting
(3.5 days)
2/5/09 start 4K wave in Yellow ring,
Hi potting (3.5 days)
2/9/09 start T7 turbine
12/12/08 Cold Snake cooldown complete, steady state.
D.L. September 17, 2008