Cryogenic System Cooldown Projection based on Full Compressor Power Starting on February 2, 2009

 

 

 

.5 MW – Dec 8, 2008 through Jan 12, 2009 (temporary peaks up to 2 MW)

 

          12/8/08 start cryo plant scrub (9 days)

          12/16/08 RHIC ring pressure testing complete, insulating vacuum established

          12/17/08 start scrub of RHIC ring (22 days)

                  

2.5 MW – Jan. 9, 2009 through Feb 1, 2009

 

          1/9/09 start 45K cooldown of cryo plant (1 day)

          1/10/09 start 45K wave in both RHIC rings (23 days)

         

6 to 8 MW – February 2, 2009 through February 8, 2009

 

          2/2/09 start 4K wave in Blue ring, Hi potting (3.5 days)

          2/5/09 start 4K wave in Yellow ring, Hi potting (3.5 days)

 

5 MW starting on February 9, 2009

 

          2/9/09 start T7 turbine

 

 

 

 

AGS Cold Snake Magnet Cooldown

 

11/14/08  Start Cold Snake Cooldown

12/12/08  Cold Snake cooldown complete, steady state.

 

 

 

 

 

 

 