MCR Shift Summaries


ALL SHIFTS, IN CHRONOLOGICAL ORDER


=================
DECEMBER  9, 1996
=================

Owl	No shift
----------------

Day	MACKAY, Fischer, Satogata				#6 p32-33
---------------------------------
	Chipmunk locations confirmed for AtR.  Instrumentation crate
in 1000P (acnfec007 or cfe-wh1-instr) back up at 1300.  Flags, BLMs,
and BPMs work on this FEC.  Flag app was run and replicated.
Yinjection app modified and replicated.
	Two timing events were missing from crossbar: FEBrequest &
FEBflatend.  Brian Oerter is looking into this.  Note: FEBbunch does
not exist according to Leif as of 1600.  This means that there is a
cabling problem with crossbar.

Eve	WEI, Dell, Brown, Satogata				#6 p34-38
----------------------------------
1. worked on AGS data archiving; The missing ones on the minimum list
   are ion charge state, atomic mass, radial loop setting, rf
   frequency, and rf voltage. The most difficult one is the correct rf
   voltage.
2. worked on RHIC data archiving (viewlog); A list of comments will be
   sent to Laster/Clifford. A list of key parameters will be
   determined after trivial bugs are fixed tomorrow.
3. Briefly tested various RHIC applications; BPM application has been
   enhanced with difference orbit saving which enables the comparison
   of actual and simulated difference orbits. 

=================
DECEMBER 10, 1996
=================

Owl	No shift
----------------

Day	MACKAY, Fischer, Satogata				#6 p39-39
---------------------------------
	Timing confusion with crossbar has been resolved.  The
FEBbunch event will be generetaed from 1004A, but is waiting on a
handshake from J Gould.
	Startup starts the current transformer pet page with a
non-standard file from Pat's area.  The following page works better:
/usr/controls/data/PetPages/BCM/readings.pet

Eve	WEI, Dell, Satogata, Thompson				#6 p40-44
-------------------------------------
1. Briefly tested various RHIC applications:
   a) Beam Profile Monitor - replicated with new features of flag
      analysis data saving for emittance evaluation (emit.out replaced
      by time stamp).  Works as desired;
   b) Various problems occurred with the following applications:
      Beam Position Monitor - can not save orbit;
      Injection Control - can not do "save magnet and orbits"
      Utilities, Transfer Matrix Calculator - not working proporly
   c) The following applications can not be started from StartUp:
      Beam Loss Monitor; Power Supplies.
2. Continue working on viewlog RHIC data archiving. Suggesting
   shot-by-shot archiving of a more complete list (in addition to
   vacuum and cryo), as well as more clean-ups.

=================
DECEMBER 11, 1996
=================

Owl	No shift
----------------

Day	MACKAY, Fischer, Tsoupas, Peggs, Trbojevic		#6 p45-51
--------------------------------------------------
1. All applications tested in detail (see list on p48).  There are
   still a number of applications down.
2. Shot archive.  Archiving possible with GPM (p50).  Data written
   into file.
3. Test of loss monitors in AGS not succesful.

Eve	KEWISCH, Ahrens, Pilat					#6 p52-56
------------------------------
    Shift goal: test the power supply manager, turn power supplies
on and ramp to the design settings ("fred file")
    The manager behaved flaky all evening until FEC009 died and
was rebooted. Thereafter, no problems.
    All atr power supplies were switched on (except for the 4 and
8 degree bends) and ramped to the design values. Switching of the
christie ps were no problem.
    The "turn all on" sequence does not handle async messages and
must be redesigned.
    A new Save/Restore interface was implemented in start-up and
tested.

Other action items:
1) stdby-fault status of ps is reported as "undef"
2) design file values must be verified (talk to nick)
3) save/restore contains bug.

=================
DECEMBER 12, 1996
=================

Owl	No shift
----------------

Day	TRBOJEVIC, Connolly, Tepikian				#6 p57-61
-------------------------------------
1. We tried to get signals from the loss monitors in the AGS tunnel.
   We found out that there are very serious problems with the PET
   asynchronous data collection.  Crates 
	FEC007 and FEC019
   have been up and down.
2. The flag program was brought up and tested.
3. A few useful tools were used.  One of them, to check if the event
   occurs on a specific FEC, is:
	ecount acnfec007 42
4. Beam was accelerated for the RHIC cycle in the AGS and the G10
   kicker was fired (with the bumps locked out).  The next check is
   the bump check when the kicker is locked as well as the septum.

Eve	KEWISCH, Ahrens, Pilat					#6 p62-62
------------------------------
1) fulvia verified and corrected the fred file (with nicks and steveTs
   help).
2) manager reliability:
	- used diffrent rpc library
	- async problem: new flush buffer function avoids 
	  death by dead messages. needs more debugging.
 	  smita had to leave at 7:30.

=================
DECEMBER 13, 1996
=================

Owl	No shift
----------------

Day	TRBOJEVIC, Connolly, Tepikian				#6 p62-68
-------------------------------------
[1] Message -- Tom Kern replaced WFG a ascvme050 crate.
[2] FEC019 went down at 10:16. L. Hoff found a bug in using "ecount".
[3] Using a simple pet page we found noise on the ULM16 BLM.
[4] We adjusted the timing in the integrater and scanned the
    MADC values with a 100us clock over 1 sec and saw a loss at ULM14.
[5] There is a timing difference between the scanned values and
    the setting in the integrator width.

Eve	KEWISCH, Ahrens, Pilat, Wei, Brown, Mane, Van Asselt	#6 p68-76
------------------------------------------------------------
1) Problems in the system software are understood, work-arounds are
available.
2) Power supply manager worked with heavy use for more than 1 hour
(still running)
3) 14 sets of initial optics files are in place.
4) Progress was made on the feb event electronics.
5) Beam/machine study with Au77 beam in AGS in preparation for RADON
longitudinal phase space reconstruction -- Mountain data is taken via
LabView of gold beam around AGS transition. The amount of phase switch
(d phi = 0.58 rad) together with ramp rate (dB/dt = 1.8 T/s) is used
to evaluate the rf voltage, and to calibrate the AGS console
reading. This information is important in accurately evaluate the
synchrotron oscillation period, and thus realistically reconstructing
the phase space motion. The AGS transition energy (user 1) is found to
be gamma=8.40. The console reading of rf voltage can not be directly
used (reading 400 kV vs. measured 228 kV at transition), and the time
calibration from AGST0 has been found not correct (see remark by Lief
A, t=0 corresponds to +335 ms).  (study performed by V. Mane, J. Wei,
K. Brown, V. Van Asselt, L. Ahrens)

=================
DECEMBER 14, 1996
=================

Owl	No shift
----------------

Day	TRBOJEVIC, Connolly, Tepikian				#6 p77-82
-------------------------------------
1) A problem of the MADC in the loss monitor was resolved! (see p78).
The integrator window shows the correct length 65 msec.  The number of
the MADC channels was reduced to **FOUR**, instead of all groups (64).
Every reading during 100 usec was correct this time.  Reading of 1
usec per scan.
2) Position of the loss monitors in the AGS tunnel are listed (see
p79).  3) The FLAG calibration plates were checked.  4) All systems
were brought up at the same time except the current in the magnets.
5) Confirmed that the TRANSFER MATRIX CALCULATOR program works
correctly!!  6) "ecount" program works fine now.  It does not crash
the FEC.  To see if an event arrives at a specific crate:
	ecount crate event
eg
	ecount acnfec007 42

Eve	No shift
----------------

=================
DECEMBER 15, 1996
=================

Owl	No shift
----------------

Day	SATOGATA, Thompson, Mane, Ahrens, Tanaka		#6 p82-101
------------------------------------------------
[1] Sanki and Leif set up bumps and kicker timing for extraction on
    user 2 flattop. There are several relevant important notes:
	(*) FEBRequest and FEBbunch are firing every user 1 cycle
		(i.e. every normal AGS cycle) for systems diagnosis
		and checkout. These can be easily turned off by the OC
		under "Spreadsheet Set CLD events, AGS real time."
	(*) If FEBRequest and FEBbunch are turned on for user 2, the
		KICKER AND EXTRACTION BUMPS WILL FIRE. These events
		should be moved away from activity by the OC when not
		in use by commissioning crews.
[2] AGS wall current monitor mountain range plots were acquired during
    user 2 flattop, approximately 50 ms before kicker
    firing. (pp. 90-93) Radon transform (still an expert activity) and
    beam measurements give a rough analysis of the extraction bunch
    (p. 100):
	(*) Bunch length:	  sigma_t    ~= 16 ns
	(*) Bunch momentum size:  sigma_p/p  ~= 1.6x10^-3
	(*) Bunch intensity:		     ~= 1.0x10^8 ions
    Radon also shows that coalescing is still unsatisfactory for BPM
    and current monitor systems.
[3] A single loss monitor (ulm14, at AGS G19) showed unmistakable beam
    losses during the user 1 slow extraction, correlating strongly
    with beam presence and BLM high voltage state. (pp. 94-99) Data
    flow from this BLM was demonstrated all the way up to BLM
    application (p. 99). Loss monitors will require retiming when beam
    arrives, but this is first demonstration of asynchronous data flow
    from BLM to application.
[4] BPM application has timing and gain interface installed, to be
    tested Monday day shift before replication. Calibration pulsers in
    A Trailer have not yet been tested.
[5] /ride file system is full, due to a FEC process logging heavily to
    subdirectories under /ride/ado/ADO/quench/acnfecq02. System cannot
    be cleaned manually; requires offending quench process to be
    killed.

Eve	No shift
----------------

=================
DECEMBER 16, 1996
=================

Owl	No shift
----------------

Day	SATOGATA, Thompson, Mane, Ahrens, Tanaka, Wei		#6 p102-116
-----------------------------------------------------
[1] Beam was demonstrated on the new H10 septum flag. (p. 103) Extraction
	is reproducable and reasonably consistent. Though more work needs
	to be done with radial loop and PUE calibration, Leif claims
	that extraction systems are operational enough for ATR.
[2] blmMan (the loss monitor manager) cannot be started from StartUp and must
	be started by a user logged into acnsun55, according to Don Shea.
	The loss monitor application was started, and Pat re-timed the
	integrators to see signals during user 2 extraction in [1].
[3] Radon studies continue, gathering more data on user 2 flattop. Discussions
	began with Mike Brennan, and present Booster-AGS coalescing was
	documented. Jie and Vibha are documenting RF and main magnet
	parameters in the AGS over cycle 2 for Radon analysis.
[4] /ride file system was restored to 200 Mb full approximately 10 AM. Tom
	Clifford claims that Tom Wild is responsible party; Fritz D is
	working coordinating efforts to avoid this problem again.

Eve	No shift
----------------

=================
DECEMBER 17, 1996
=================

Owl	No shift
----------------

Day	SATOGATA, Thompson, Mane, Ahrens, Tanaka, Wei		#6 p116-125
-----------------------------------------------------
[1] EXTRACTION: Timing work on bumps resulted in extraction setup that
	can deliver, with appropriate RF conditions, two extracted
	bunches in one AGS cycle.
[2] BLM STUDIES: BLM application and manager are still having
	robustness problems. '95 ATR timing was loaded and, using a
	pet page, clear loss signals were seen at the septum when FEB
	extraction was fired, timing off of FEBbunch. Data was also
	taken showing two-bunch extraction mentioned in [1].
[3] BPM SETUP: BPM systems were set up with nominal ATR timing as last
	year, and non-beam triggered acquisition on the user 1 cycle
	was seen from all channels. Triggers have been left on to
	probe orbit manager for high-data rate memory leaks. Delay
	module aliases were installed into
	/ride/config/adoaliases. Gains set to +20 db, but remain to be
	checked with calibration pulsers.
[4] RADON STUDIES (from Jie): Beam/machine study with Au+77 beam in
	AGS ATR/Sextant cycle (User 2) to test RADON longitudinal
	phase space reconstruction, and to evaluate longitudinal bunch
	size. Various timings in AGS User2 have been calibrated:
		Booster cogging_arm_rf	 	  33ms after AGS T0
		AGS rf voltage reading origin    217ms " " "
		transition			1100ms " " "
	The AGS transition energy is found to be gamma_t=8.49. With
	the known ramp rate (dB/dt=2.0 T/s) and synchronous phase
	(0.58 rad) evaluated at transition, the actual rf voltage is
	found to be about 72% of the console "scaler voltage"
	reading. With these information, RADON has been used to
	reconstruct longitudinal phase space at User 2 extraction.
	The evaluated bunch parameters at AGS user 2 extraction are:
		sigma(t) = 8.3 +/- 1 ns
		sigma(p) = 7.8 +/- 1 x 10^-4
		S (95% bunch area) = 1.4 +/- 0.3 eV s/u
		intensity 1.0 x 10^8 ions/bunch

Eve	No shift
----------------

=================
DECEMBER 18, 1996
=================

Owl	No shift
----------------

Day	WEI, Dell, Mane, Tsoupas				#6 p126-140
--------------------------------
1. RADON application: Error sensitivity study shows that RADON
   longitudinal phase space reconstruction requires an accurate
   knowledge of synchrotron oscillation period (at 5% level).
   The instruction for running RADON is posted in logbook 6,
   p. 132-136.
2. EMIT application: The instruction for running EMIT for transverse
   emittance measurement using U-line flags is posted in log book 6,
   p. 137.
3. AGS shot archive: The instruction for AGS shot archive has been
   posted in logbook 6, p. 50. Missing information includes AGS
   current transformer reading, charge state, atomic weight, rf
   voltage, and radial loop function. Further work will be done to
   pass AGS cycle number to RHIC applications.
4. Viewlog application: Cryo information up to 12/16/96 is now
   available.  Vacuum data is partially available for 12/17/96 and
   12/18/96.  Viewlog will be replicated in a day while further worked
   on by J. Laster to include maximum and minimum values etc.

Eve	No shift
----------------

=================
DECEMBER 19, 1996
=================

Owl	No shift
----------------

Day	WEI, Dell						#6 p140- #7 p4
-----------------
Viewlog application testing and development --- 
The newly replicated application includes Utility, Cryo, and Vacuum:
1. Utility includes utility box temperature of 16 crates, all data
   logged up to the current time. All but util.007 (showing a constant
   73.0 degree) are credible.
2. Cryo contains cryogenics data of 60 entries, all logged up to the
   current time. Displacement data of YO4-CRT6 and two DU3 are
   expected to be available on 12/20/96. 
3. Vacuum status including W-line, X-line, and Y-line ion pump and
   CCG gauge pressure is logged properly reflecting PET page values.
   Information on U-line is not available due to data transfer
   problem.  Information on the sextant is expected to be available in
   1 to 2 days.

Eve	No shift
----------------

=================
DECEMBER 20, 1996
=================

Owl	No shift
----------------

Day	WEI, Dell, Mane						#7 p5-28
-----------------------
1. Viewlog application development for RHIC data logging --
   Vacuum data (ion pump and CCG pressure) for all AtR lines (U, V, W,
   X and Y line) and the sextant have been logged. Viewlog reported
   ion pumps working for all AtR units except for xip5 and yip5, and
   for sextant units YO5-IP-PW7.1 and YO5-IP-PW7.2 at pressure level
   of 10^-9 to 10^-8 Torr.
   Cryogenics data logged includes all but 4 recooler outlet
   temperature reflecting room temperature before coll
   down. Displacements data for YO4-CQT6 magnet and two DU3 dummies
   are all logged, with an agreement with expected values between 1
   and 5 mils.
   Utility data including 16 crate utility box temperature are
   continue to be logged. A reading of constant 73.0C for FEC007 is
   reported to be caused by a faulty thermal sensor.
2. Radon application development for longitudinal phase space
   reconstruction --
   Various timing values have been recalibrated for AGS User 2 (for
   sextant test) to reflect the recent change in rf program. The new
   timings are:
          Booster Cogging_Arm_RF:   27 ms from AGS t0
          AGS transition:         1587 ms from AGS t0
   More mountain data have been collected for Radon testing.

Eve	No shift
----------------

=================
DECEMBER 22, 1996
=================

Owl	No shift
----------------

Day	KEWISCH, Pilat						#7, p29-35
----------------------
1) Conclusion: The measurement of Resistance and Inductance [of power
supply/magnet circuits] works but involves many manual steps.  The
analysis of the data will be done off-line.
2) All PS ramped to 98% of maximum.  "utv2.2" tripped at 80%.
3) "Wireup" database corrected.

Eve	No shift
----------------

===============
JANUARY 6, 1997
===============

Owl	No shift
----------------

Day	WEI, Dell, Brown, Mane					#7 p38-54
------------------------------
1. RHIC data logging by ViewLog: Data logging over the past four
   days indicates a displacement of about 7 mils transversely on
   YO4-CQT6 and longitudinally on YO5-DU3, which is correlated to
   magnet loop pressure change of about 16 PSIA. Further effort
   is made to build tree structure (regrigerator, valve box, recooler)
   in the cryogenics branch.
2. AGS shot archiving: Now the shot archiving includes long desired
   information including charge state, atomic mass, rf voltage
   (scaler), rf frequency, radial loop reading, along with B field,
   AGS extraction kicker G10, Bump G9, H11 readings, and cycle number.
   The time of logging is set to 2200 ms after AGSt0 (current
   FEBrequest).
3. RADON longitudinal beam tomography: Various timing is done once
   again, and data is taken over the whole AGS cycle to evaluate
   the longitudinal bunch emittance growth. 
4. G09B bump is down and being worked on.

Eve	No shift
----------------

================
JANUARY 10, 1997
================

Owl	No shift
----------------

Day	MACKAY et al
--------------------
No summary.

Eve	WEI, Dell, Brown, Ahrens				#7 p60-p76
--------------------------------
1. Main Progress: Gold beam extracted from AGS, steered down the
   U-line passing 8 degree bend, showing up on flag uf3.
2. AGS extraction: Nicely shaped gold bunch of 20ns full width, at
   intensity of about 5x10^7, were extracted from AGS. The position of
   the flag image on u-line uf1 was centered by adjusting H10 septum
   current. The timing between FEBrequest and FEBbunch is 28ms
   (compared with last year's 31ms).
3. With the dead-reckoned current in the U-line, the beam image shows
   up on the first 3 flags (uf1, uf2, uf3), though not centered. At
   the first shot, current transformer recorded 3.2x10^7 particles,
   and beam loss monitor is also showing high loss readings. The
   starting current file is fred-90-80.
4. Lattice tuning: With tuned H10 current, the beam is centered
   horizontally on uf1; with tuned 4 degree arc, the beam is also
   centered on both uf2 and uf3. The beam is nearly centered
   vertically by adjusted trims tv1, tv2.2, and tv3.
5. Problems occurred:
   a) PS page "maxLevelS" was not set to "Bits" -- fixed;
   b) AGS septum and kicker were having non-hardware problems, septum
      current was set wrong -- fixed;
   c) 8 degree and 20 degree PS were left at local -- fixed;
   d) FEC007 computer was down -- rebooted and fixed;
   e) Flag application was complaining insufficient memory when one
      hits "Ctr D" to retrive other flag images other than the last one
      -- not fixed, occurred from time to time;
   f) Vacuum valves at WSV6, WSV7 and the two in Y line still closed 
      -- not fixed, MCR doesn't know how;
   g) Flag application complained "failed to fit a Gaussian" even with
      a decent profile.
6. Manu: Various start-up instructions were indexed on the second page
   of Log Book #6 and #7.

================
JANUARY 11, 1997
================

Owl	SATOGATA, Mane, Thompson, Tom Shea			#7 p77-p90
------------------------------------------
1. Main Progress: Gold beam delivered through W-line to W-line
   flags. All instrumentation except BPMs is working. 4-degree and
   8-degree bends scanned.
2. Intensities vary from 1.0 to 4.0x10^7 ions delivered by the
   AGS. These are intentionally being kept low by the AGS while tuning
   is being performed.
3. Tuning: Hysteresis runs are necessary. Hysteresis run on 8-degree
   bend at beginning of last shift practically delivered beam
   immediately to W-line.  Small vertical adjustments and tuning
   delivered beam to W-line flags.
4. Beam loss monitors at ulm6 (8 degree bend) are correlated to beam
   presence, but heavily saturated. Scans of 4-degree and 8-degree
   bends were unable to bring these loss levels down.
5. Problems:
   a) BPM system is still problematic. Manager problems are being
      worked on by Todd, and cables for railed BPM planes (ubh2, ubh6,
      ubh8, ubv4, ubv8) will be checked. acnfec019 was rebooted at
      1:20 to work around a known bug in reloading BPM ADO's. BPM
      configurations were also fixed.
   b) Vacuum valves WSV6 and WSV7 are still not open; beam still
      appears, though widely dispersed, on flags wf1-3.
   c) Flag profiles still show interlacing problems (pp. 78-9). It is
      also unclear whether to believe positions as given by 2d graphs,
      or by flag axis marks. Many times these differ by several mm!

Day	MACKAY, Fischer, Tsoupas				#7 p91-p97
--------------------------------
Had beam at wf3.  Sector valves wsv6 and wsv7 were left in.  We has a
vacuum dude come in to fix this since the target desk didn't know the
password.  Major problems with U-line BLMs.  There are probably losses
at the front end, but we were unable to tune the line with faulty
hardware/software (BLM).

Eve	WEI, Dell, Brown, Satogata				#7 p97-p123
----------------------------------
1. Main Progress: Gold beam has been steered down to the end of ATR
   dump, using either the first (uf1) or the second (uf2) flag as
   striping foil.
2. An orbit (PS file Jan.11.96.owl) has been established to steer the
   beam to the ATR dump with uf1 as striping foil, and with uf2 out.
   A second orbit (PS file Jan.11.97.23:10) has been established to
   steer the beam to the ATR dump, with uf1 out. For both orbits, beam
   images show up on all U and W line flags.
3. Both uf1 and uf2 have been shown to significantly change the
   momentum of the beam, in addition to striping. Tuning with/without
   these flags must take the momentum shift into account (known from
   last year's study).
4. BPM application is partially working, agreeing with flag image
   readings.
5. AGS extraction condition has been completely archived (p. 105 -
   109, #7).  Shot archiving program is further improved on rf
   frequency reporting.
6. RHIC data archiving continuing, with data over the past 16 days
   showing sextant vacuum conditions (YO5-ip-pw7.1, pw7.2, pw9.1,
   pw9.2 at 10^-9 torr level).
7. Problems:
   a) Both AGS bumps were down, several times;
   b) Flag application: both frame grabber 3 and 4 are have problems
   -- not fixed
   c) Magnet manager was down three times; restarted;
   d) BPM manager was down twice, reportedly fixed;
   e) Power supply pswq2 was tripped, soon brought back.
   f) Current transformer application was not working.
   g) Flag wf2 shows "middle" when put in.
   h) RHIC archiving: crate temperature high (~ 55 C) on fec007 and
   fec013.

================
JANUARY 12, 1997
================

Owl	SATOGATA, Mane, Thompson				#7 p124-p138
--------------------------------
1. Main Progress: U-line completely tuned with uf2 flag as stripping
   foil, giving near-100% transmission to current transformer uxf3, no
   losses, and a flat orbit. W-line still needs tuning and
   flattening. These are stored in the 'Jan.12.97.07:43' magnet save
   file.
2. Dave Gassner and John Donahue tune AGS extraction intensity through
   the night, wiht clear indications of improvement. (p. 126) Early
   morning extraction intensities rose to 7.5x10^7 ions/bunch through
   the U-line.
3. Mountain-range data acquisition was set up for longitudinal
   emittance measurements; synchrotron period at extraction was
   measured to be 8.2 ms.  Setup encountered scope problems and AGS
   vacuum problems; measurements are planned for tomorrow night's owl
   shift.
4. BPMs were showing good data early in the evening, though later they
   began to fail again.  BPM manager dies every 32 acquired
   orbits. Timing will be checked again later on in day on Sunday
   shift. A difference orbit using uth2 was generated (p. 136). This
   can be compared directly to TransMat.
5. Loss monitors and current transformers were restored to operation by
   following two setup files listed at the bottom of p. 124. Current monitor
   noise was measured at ~5x10^6 ions/bunch. Only main beam losses are very
   near the end of the W-line.
6. Problems:
   a) BPM Manager dies after 32 acquired orbits; no way to reattach
      running OrbitDisplay application to newly started BPM manager.
   b) BPMs are still giving underflow and triggering errors even with
      strong beam intensity. Some bpms (e.g. utv8) are never working
      properly, and marked to be checked by instrumentation personnel.
   c) OrbitDisplay dies occasionally when generating difference orbits.
   d) Frame grabbers 3 and 4 continue to be problems; intermittently
      working.

Day	MACKAY, Fischer, Tsoupas, (Thompson, Satogata)		#7 p138-p148
------------------------------------------------------
1) Tuned line for lower losses.  Archived settings saved in
   "Jan11.97.01:45" <-(pm)
2) All current transformers were working.  wxf1 may need to be timed
   in a little better.
3) We need to check magnet bends versus transfer matrix.  Possible
   problem with scale factors?
4) New version of bl-steer which can change ubegin vector.

Eve	KEWISCH, Ahrens, Pilat, Satogata			#7 p149-#8 p3
----------------------------------------
goals: 	1) calibration of flag uf3 to center of quadrupole uq12.
       	2) trouble shooting wtv6.
	3) prediction vs. measurement of difference orbits.
	4) calibration of the current transformers.
accomplished: 
	1) the flag uf3 is vertically about 10 mm off center
	   relative to  uq12. the measurement of the horizontal
	   misalignment is inconsistent.
	2) the wtv6 power supply was changed before any testing could
           be done.
	3) bcms show 70% beam loss between the 1st and 2nd bcm. blm do
	   not work and are necessary to confirm the loss.
	4) bpms in w-line not responding for most of the shift.
	   difference orbit measurement was not tried.

================
JANUARY 13, 1997
================

Owl	SATOGATA, Mane, Thompson				#8 p4-p22
--------------------------------
1. Main Progress: Nearly 100% transmission through ATR achiveved with
   minimal losses, repeatably showing 8x10^7 ions on all current
   transformers. Diff orbs with BPMs appear to indicate old
   factor-of-two turn problem in U-line dipole correctors
   (pp. 9-11). Longitudinal bunch size (95% bunch area) is 0.3
   eV-sec/nucleon, with a single 12-to-6 coalescing in AGS.
2. Extraction: extraction remained quite consistent, with perhaps 20%
   failure rates on extraction bumps. Beam placement on H10 flag
   checked and correct. Delivered beam intensities were consistent at
   7-8x10^8. Current transformer wf3 was timed in correctly (pp. 16-17).
3. Mountain-range data acquisition was set up for longitudinal
   emittance measurements; additional data was taken, and the previous
   night's data was analyzed to give 95% bunch area of 0.3
   eV-sec/nucleon. We anticipate that Mike Brennan's coalescing
   efforts will raise this value.
4. A new BPM application was replicated, allowing for simulated
   difference orbits given a single dipole corrector setting.
   Difference orbits were compared to measured difference orbits for
   utv1 and uth2, apparently showing that dipole correctors are a
   factor of two stronger than we intend them to be -- is this the old
   dipole corrector turn problem? Transmat and simulation are
   consistent with each other.
5. BPM system timings were checked, although some BPMs (e.g. ub8) are
   still not showing good data. These will be discussed with Tom
   Shea. At these intensities, BPM plate voltages are >100 mV, and
   signal is very clean. BPM Timing is characterized on p. 18.
6. Problems:
   a) OrbitDisplay dies occasionally when generating difference
      orbits.
   b) BPMs are still giving underflown and triggering errors even with
      strong beam intensity. Some bpms (e.g. utv8) are never working
      properly, and marked to be checked by instrumentation personnel.
   c) Frame grabbers 3 and 4 continue to be problems; intermittently
      working (p. 4)
   d) acnfec007 had to be rebooted when it slowed and became
      unpingable (p 6)
   e) Some flags show large beam offsets even with 100% transmission
      efficiency

Day	TRBOJEVIC, Connolly, Tepikian				#8 p23-27
-------------------------------------
1) The BPM signals from the U line were not coming out, half of the
   shift
2) We set the beam at the end of the W line at the quad WQ5 correctly
   (used WPS2 from 381.787 A down 373 A).  The beam position on WF3
   has not changed at three WQ5 currents: 194 A, 175 A, and 150 A.
3) We found out that the beam was off site on the WF1 flag!!  We found
   that even on UQ5 (upstream) the beam was off the center of the quad.
|  WE REALIZED THAT THE WHOLE BEAM LINE HAS THE BEAM GOING OFF THE
|  CENTERS OF THE QUADS.
4) Started to "tune" the beamline from the UF2 flag.  We found that
the UQ5 shows the beam off the center of the quad.
5) At 1:30 pm the AGS is down.

Eve	KEWISCH, Pilat, Ahrens					#8 p28-30
------------------------------
No beam until 11:30 pm.
Corrected u-line trim transfer function and verified beam deflection.

================
JANUARY 14, 1997
================

Owl	WEI, Dell						#8 p31-39
-----------------
1. Main Progress: The transmission efficiency of u-line reach 100%,
   and the efficiency in u+w line reaches 90% (PS file
   Jan.14.97.08:00), achieved by tuning vertically the elements utv4,
   utv7, wp1, wp2.
2. Tuning: After the change in PS database, an earlier file with 30%
   transmission was used to start tuning. 100% u-line (uxf3/uxf1) was
   achieved by adjusting utv4 strength. 90% u+w (wxf1/uxf1)
   transmission was achieved by adjusting utv7, wp1, and wp2 strength.
3. After tuning, vertical center readings of all u and w line flags
   are within 3mm from flag origins.
4. Tuning was preliminarily done with 3 current transformer readings,
   u-line loss monitor, and u+w flags.
5. Problems:
   a) BPM not working properly (e.g. ubv7 not responding like uf3 on
      trim);
   b) w-line loss monitors not working properly (e.g. when u-line
      transmission is 100% but w-line 10%, w-line BLM not recording
      loss);
   c) Flag centroid reading often does not agree with center reading
      (center reading is ok);
   d) Magnet manager and application were hung many times -- fixed by
      killing the manager on acnsun16 and restart manager;
   e) BPM applications often dies after a certain time period;
   f) Frame grabber 3 and 4 of flag application not working.
6. Typical u-line BLM reading recorded for various cases including
   uf2 in and 100% transmission (uf1 out), both uf2 and uf1 out, 
   high u-line loss, etc.
7. 8 degree bend dipole strength scanned against transmission
   efficiency and uf3 position readings.

Day	TRBOJEVIC, Tepikian, Connolly, Mackay			#8 p40-41
---------------------------------------------
Day shift had problems with BLM application early in the day.
SUMMARY: Did some fault studies -
 1) warc20 appears to be a good critical device for RHIC running.
 2) With final RHIC intensities, the survey shaft by wp1 may give
    levels of ~250 mrem/hr.  Either the berm will have to be swept or
    the survey shaft will need to be covered.
Half of the required fault studies have been completed.  Try again
tomorrow.

Eve	KEWISCH, Pilat, Ahrens					#8 p42-50
------------------------------
1. Double ejection: septum fails to recharge, technician called.
2. BPMs: problems with trigger at low intesity, no useful measurement
   possible.
3. Emittance measurement successful, emittance imaginary.
4. flag uf3 alignment measurement to be continued. (injection
   p.s. problems in ags)

================
JANUARY 15, 1997
================

Owl	WEI, Dell, Brown					#8 p52-70
------------------------
1. Main Progress: Both U and W line are tuned with the beam going
   through approximately the center of all the flags. The lattice
   (PS file Jan.15.97.04:20) is suitable for emittance measurement.
   Momentum aperture scan and dispersion measurement are done on
   AGS extraction, U and W lines.
2. Tuning: The ATR line was tuned with the beam going through the
   center of all (except uf5 H) flags. The u line transmission is
   100%. W line transmission is above 90%. The lattice is adequate for
   emittance measurement use.
3. Momentum aperture scan: The momentum aperture of AGS, U, and W
   lines were scanned by changing AGS radial orbit position, while
   simultaneously recording AGS rf frequency, current, U and W line
   current transformer readings, and center positions on all the u and
   w line flags. BPM positions are archived for each orbit. Loss
   monitor readings are logged in the logbook for each orbit
   also. Further analysis will yield momentum aperture.
4. Dispersion measurement: The dispersion at all flag locations will
   be available after aperture scanning data being
   processed. Dispersion at BPM locations is unknown, depending on
   analysis of archived BPM data.
5. Reproducibility study: Repeatibility of beam positions and
   intensity at ATR entrance were studied by recording uf2 position,
   AGS shot current, and uxf1, uxf3, wxf1 current readings for 9
   different AGS orbits.
6. Emittance measurement preparation: attempted to archive data for
   emittance evaluation using EMIT.
7. Problems:
   a) FEC009 was down, rebooted, and PS restarted;
   b) AGS L20 septum was down;
   c) Current transformer uxf1, uxf3 were broken - fixed by Pat;
   d) Loss monitor application were down - restarted manager;
   e) pswq1 PS was on Stby-Fault - reset easily;
   f) Flag application will die if EMIT was set on for two flags. It
      would be highly desirable if 1-D fit Gaussion could also be
      shown along with actual profile, and if EMIT saving could be
      activated only after the flag image is checked to be acceptable.

Day	TRBOJEVIC, Tepikian, Connolly				#8 p71-72
-------------------------------------
1) We tried (Roger Connolly) to get the IPM working (detailed report
   will follow).
2) The magnet file from the previous shift showed high losses in both
   the U and the W lines.  We reloaded the file Jan.14.97.12:27 which
   has low losses but is not in the center of the flags.
3) We found that the previous settings UQ9 beam was off the center.

Eve	MACKAY, Tsoupas, Fischer				#8 p73-85
--------------------------------
1) Had beam to dump with multiple extraction (2 pulses per AGS cycle).
2) Took uf2 position data while scanning quads uq1->5 for offline
   analysis.
3) BLM application has some inconsistencies for can-to-signal
   assignments.  Some signals, eg "ylm8", seem to be missing.
4) Transverse emittance measurements e^N_95 = 10x10^(-6) [m].
5) Found bug in Yinjection App.  Has been fixed but not replicated.
   Works for vertical bumps.  Hard to prove for horizontal due to AGS
   extraction wobble.
6) Had 1.3x10^8 ions extracted in a single bunch.

================
JANUARY 16, 1997
================

Owl	WEI, Dell, Brown					#8 p86-107
------------------------
1. Main progress: Transverse emittance, measured with AGS IPM to be
   about 10 mm mr, agrees with that measured in the U
   line. Lattice functions, evaluated for all the u and w line flag
   locations, agree with design values at 20% level. Momentum
   aperture dispersion scan done for both u and w line with fixed
   AGS extraction condition.  
2. Emittance measurement: With IPM in AGS, the measured emittances are
      Ex = 10.1 +/- 0.7 mm mr
      Ey =  9.6 +/- 0.9 mm mr      (normalized 95%)
   agreeing with that measured in the U line with flags uf3, uf4, uf5.
3. Beta function measurement: Using all 8 u and w line flags, tuned to
   avoid saturation, the beta functions at flag locations are obtained.
   Comparing with the design values, the deviations are:
      D(beta)/beta (x) = 0.1 +/- 0.3
      D(beta)/beta (y) = 0.2 +/- 0.5.
4. Momentum aperture: With fixed AGS extraction, the momentum
   apertures are obtained as:
      A (u-line) = 2.9 %
      A (w-line) = 1.2 %
   (Gamma acceptance: 12.15 +/- 0.18 (u-line); 12.15 +/- 0.07 (w-line))
5. Line dispersion: 14 orbits are taken for u and w lines, with fixed
   AGS extraction, recording simultaneously loss monitor reading, BPM
   archiving, all flag centers, and all u+w current transformer and
   AGS extraction current readings. Data to be processed.
6. Lattice comparison: Lattice (Jan.14.97.14:07) is found to have a
   transmission of 100 +/- 3%. However, since flags (e.g. uf5) can be
   off scale, caution should be taken when using it for emittance
   measurement. Lattice (Jan.15.97:04:20) has all flags
   centered. However the transmission is 92 +/- 3%. The loss is at 20
   degree bend, possibly caused by mis-centered uf5.
7. Flag uf5 is suspected to be off center vertically by -1 cm, based
   on deviation from BPM reading and loss monitor tuning.
8. U-line BPMs are all working, with difference orbits within 1 mm
   from what predicted by design model. W-line BPMs are not working.
9. Problems:
   a) Sigma reading from fitted Gaussian of the flag application seems
      not reliable. E.g., uf5 sigma(x) and sigma(y) suspected exchanged.
   b) PS pswp1, pswp2, pswq2 tripped and reset.
   c) PS application stoped several times for no obvious reason;
      manager restarted each time.

Day	SATOGATA, Thompson, Mane, cast of thousands		#8 p108-117
---------------------------------------------------
1. IPM: Background subtraction and comparisons attempted with no
   conclusive results. Attempt to switch polarity of power supply
   showed no appreciable changes.
2. Intensity and RF Tuning/Maintainence: Tandem tuning, a new foil,
   peaker tweaking, and BTA tuning have given reliable intensities of
   9-10x10^7 ions for the majority of the morning shift.
3. BPM Update: BPM problems in W-line diagnosed as a configuration
   problem. These will be fixed early in evening shift. BPM timing and
   gains set up to produce reliable triggering and readbacks for
   intensities above 8x10^8 ions. Intensities as reported by BPMs
   appear to scale quite well from shot to shot (p. 113)
4. RF had the beam for an AGS RF module replacement from 1130 to
   1300. Further RF repair and returning continued to 1400. Fault
   studies began at 1430 and continued to well beyond end of shift.
5. Problems: 
   a. BPM configuration in W-line is incorrect for channels wbv2,
      wbh2, wbv3, wbh3, wbh4. These will be fixed in the early evening
      shift, and further BPM studies will commence.
   b. Repeated AGS and RF tuning appeared to require retuning of the
      AGS extraction kicker several times. This can be diagnosed using
      the H10 flag (p. 113).
   c. Some BLMs were apparently missing from the application
      readbacks. These were fixed in consultation with Don Shea.

Eve	MACKAY,	Ahrens, Fischer, Tsoupas			#8 p118-127
----------------------------------------
1) Todd made the BPMs work.  They were running for the rest of the
   shift.
2) Horizontal and vertical orbits flattened using the BPMs.
    peak-to-peak horizontal ~ 7 mm
    peak-to-peak vertical   ~ 5 mm
   Steering was done manually and with 4 bumps
3) Losses in Fig 2 p126 are due to the uf2 flag.  One can see this by
   taking uf2 out.  The losses disappear but beam hits the 8 degree
   bend dipoles.
4) Emittance was measured using uf3,4,5.  See p123.  Also a measure of
   emittance blow up.  See p123.

================
JANUARY 17, 1997
================

Owl	KEWISCH, Ahrens, Pilat					#8 p128-137
------------------------------
1) leif adjusted the kicker timing, changed the horizontal injection.
2) horizontal orbit correction using the BPMs
3) verified misalignment of uf3 and uf5 with bpms.
4) emittance measurement using wf1-3. ex = 9.4 pi, ey = 20.3 pi ???
5) emittance measurement using uf3-5, ex = 12, ey = 12.6.
6) tried to use w-arc dipols at nonimal tsrength, but orbit correction
   does not work.
7) saved file as jan-97.07:30
8) leif reduced some of the vertical coherence at ags injection.

Day	SATOGATA, Mane, Thompson, more of the cast of thousands	#8 p138-149
---------------------------------------------------------------
1. Main Progress: Archived systematic orbit data for single-bunch and
	multi-bunch extraction and saved to correlate with beam
	current.
2. Extraction: Intensity has been erratic, ranging from 4 to 7x10^7.
	RF work by Mike Brennan continues, with plans to attempt the
	next stage of coalescing on Sunday evening. LTB and BTA tuning
	must be watched closely by AGS operations to maintain high
	intensity.
3. BPM status: Orbits were acquired for multiple-bunch extraction, and
	appear to correlate well with FEB expectations.
4. Flags: Larry appeared to work on Flag timing, and it seems the
	framegrabber 3/4 and interlacing problems are understood as
	being caused by staggered acquisition timing.
5. Applications:
   a) BCM no-beam offsets were placed into the current monitor ADOs
      (p. 141).
   b) New BLM app only displays new data when acquiring
      continuously. Yaay!

Eve	MACKAY, Fischer, Tsoupas, Satogata			#8 p149
------------------------------------------
No useful measurements (some days you should just stay in bed).
Problems with Magnet Manager and missing event 42.  The beam was
pretty erratic.

================
JANUARY 18, 1997
================

Owl	KEWISCH, Ahrens, Pilat					#8 p150- #9 p7
------------------------------
1) leif adjusted the kicker timing again and the positions on the h10
   and uf1 flag are documented.
2) the magnet manager locks up frequently, when the global "doit"
   function is used. last night the manager locked up only once during
   the shift.  It is documented that the manager hangs in the network
   routines.
3) Through the rest of the night the BPMs produce "lies": orbits are
   displayed when the beam is lost or not ejected from the ags,
   positions dont chage when upstrem dipoles are changed
   drastically. the bpms are useless.
4) the 60-80 optics is used: first a fresh start from the design file,
   then including the "corrections" from the 90-80 optics. the beam is
   lost in the w-arc.
5) the emittance is measured in the u-line using flags uf3, uf4 and uf5 
	ex = 11.5, ey = 11.4
6) multibunch extraction with 4 bunches is tested. the extracted
   bunches seem to be spread horizontally. the bpms pick up all 4
   bunches.

Day	SATOGATA, Mane, Thompson				#9 p7-9
--------------------------------
1) Safety sweeps and procedures aee done for the day.
2) 4 degree bend is back on: 8 degree bend still in local.  Switch, X,
   Y arcs are locked out.
3) Frankel says that tomorrows sweep check procedures shoud impact AtR
   minimally.
4) BPMs, BLMs, BCMs should be working for evening shift.

Eve	TRBOJEVIC, Connolly, Tepikian, Peggs			#9 p10-13
--------------------------------------------
Got beam off IPM and saw good signal from electrons.

================
JANUARY 19, 1997
================

Owl	No shift
----------------

Day	No shift
----------------

Eve	SATOGATA						#9 p14
----------------
1) AGS down for user 2 for most of the day for fsiled RF module
   replacement.  Restored @ 1700.
2) All beam in AtR vanishes for 4-8 hours while Brennan tunes AGS RF
   coalescing.
3) Magnets were left in state of Jan.17.97.07:30 to keep houses warm!
4) Left Orbit, Flag, & Loss Monitor apps up to test for stability.

================
JANUARY 20, 1997
================

Owl	No shift
----------------

Day	WEI, Dell, Brown					#9 p15-23
------------------------
1. RHIC cool down and data archiving: RHIC cool down started. Viewlog
   archive showed practical readings of Helium flow for refrigerator
   and flow to load. Various vacuum readings (yo5-cc-pi8.2,
   yo5-tc-pi8.2, etc) archived. The insulating vacuum reading
   bi5-cc-pc1, more directly indicating the cool down, is however not
   available through viewlog.
2. AGS archiving: AGS rf frequency is now archived with more than 50%
   chance on the same archive page. 
3. Problems:
   a) FEC018 reported problematic - rebooted;
   b) Coalesced AGS beam shows a double peak about 100ns apart,
      arriving at two different spots on H10; reset to non-coalesced
      setting;
   c) AGS main magnet overheated and down for 3 hours, rf tripped;
   d) AGS extraction not stable, and at unusual H10 position; needs
      work;
   e) psuq3 tripped, psutv1, utv5, utv7 stby, could only be set back
      by target guys;
   f) u line pet page WFG not updating -- rebooted FEC009;
   g) RHIC 4 o'clock service building roof fan reported on, cold,
      water on floor.

Eve	TRBOJEVIC, Tepikian, Connolly, (Wei, Ahrens)		#9 p24-30
----------------------------------------------------
1) After tuning the end of the U-line and W-line we could never get
   rid of the losses at the IPM ylm8.1
2) During the whole shift the beam was pretty stable and none of the
   applications tripped off.  The BPMs showed movement of the beam
   consistent with the flags.
3) Horizontal and vertical scans by pswtv6 & pswth5 through the who;e
   aperture have never reduced losses at ylm8.1
4) The IPM background corresponds directly to the reading of the loss
   monitor ylm8.1
5) If the losses at ylm8.1 could be lowered from their present range
   of 5400 to 6300, down to 300, the IPM would be able to have normal
   backgrounds.

================
JANUARY 21, 1997
================

Owl	No shift
----------------

Day	WEI, Dell, Brown, Mane et al				#9 p31-46
------------------------------------
1. Stability of multi-bunch extraction: BPM recording of 4-bunch
   extraction from AGS shows that variation in transverse trajectories
   to be of order of 1 mm or less. Pulse-to-pulse variation of BPM
   reading is also of the order of 1 mm over a time period of 30
   minutes. The variation of intensity (on uxf1) amoung 4 bunches is
   similar to that between pulses.
2. RHIC cool down: Viewlog archive shows the decrease of sextant
   recooler outlet temperature (yo5-q6, yo5-q14, yo5-q21, yo4-q14,
   yo4-q6), reaching below 80K. The longitudinal displacement on
   yo5-du3 is shown to be above 150 mil, that on bi5-du3 remain near 0.
3. AGS, u, and w line dispersion:
   The dispersion at u and w line flag locations is shown to be
   significantly different from both the design and last year's
   measured value.
	Flag	measured (m)	design (m)	last year's measure (m)
	uf2	2.2		2.3		2.0
	uf3	-0.5		0.0		0.0
	uf4	-1.5		0.1		-0.1
	uf5	-0.5		0.0		-0.2
	wf1	-1.9		0.0		-0.4
	wf2	-0.3		0.0		-0.1
	wf3	-1.1		0.0		-0.2
4. AGS, u, and w line momentum aperture:
	line	full aperture Dp/p
	AGS	1.0 %
	U	2.9 %
	W	1.2 %
5. Problems:
   a) Flag application can not handle multi-bunch pulse (showing 3 out
      of 4 profiles with identical image);
   b) PS uq1, uq2, uarc4 tripped, uq1 reset by target group.
   c) BPM ubh8 and ubv8 not functioning.
6. Tuning: PS file Jan.17.97.07:30 shows transmission of 91 +/- 7%.
   BLM shows loss at 8 degree bend and near ATR dump. BPM reading
   shows that horizontal injection position has changed 3 mm from that
   of last week. The injection angle has also changed.  (correction:

Eve	No shift
----------------

================
JANUARY 23, 1997
================

Owl	No shift
----------------

Day	WEI, Tanaka, Tsoupas, Mane, Van Asselt, et al		#9 p49-62
-----------------------------------------------------
1. Reset AGS FEB extraction point: It is found that FEB extraction
   condition is significantly different from last year's at AGS. The
   transverse tunes were inproperly set with missing points at
   FEBrequest (used for RF dipole study instead). The sextupoles were
   inproperly set to 100 A. The newly set and measured tunes at AGS
   are:
             Set         Measured
     H       8.77        8.72
     V       8.75        8.80
   with bumps off. The horizontal tune is expected to decrease, and
   the vertical increase, as bumps are turned on. The sextupoles are
   set to 50 A, avoiding beam disruption when bunps are turned on (one
   sextupole is sitting on the bump). AGS main field and rf frequency
   at extraction are found to be the same as last year's.
       B0 = 11.225 kG,    f(rf) = 2.961 362 MHz.
2. FEBrequest timing shift: Since the AGS main magnet function has
   been changed recently to start the flat top at 2200 ms (instead of
   2000 ms) after AGSt0, the FEBrequest event is delayed by 100 ms to
   FEBrequest = 2300 ms after AGSt0.
3. Emittance measurement in AGS: Emittance is measured again in the
   AGS with IPM for User2. The new values are
       E(x) = 11.3 +/- 1 mm mr
       E(y) = 12.0 +/- 1 mm mr.
   Note that the fitting argorithm of IPM application often gives
   incorrect result. So, double check before concluding results!
4. RHIC cool down: Viewlog shows recooler temperature reaching 4.5 K.
5. Problems:
   a) BPM data taken on 1/15/97 for dispersion evaluation is no good.
      Measurement needs to be repeated later when everything is
      stable, and after we finish things of higher priority.
   b) AGS IPM application often give incorrect fitting and emittance
      result even with decent-looking profiles.

Eve	No shift
----------------

================
JANUARY 24, 1997
================

Owl	No shift
----------------

Day	No shift
----------------

Eve	WEI, Dell, Brown, (Peggs, Mane, MacKay, Kewisch, Satogata, et. al)
------------------------------------------------------------------	#9 p63-70
1. Sextant Commissioning Approval: The approval has been
   granted. Sweep was done to the ATR lines and the sextant. Final
   safety checkup still going on.
2. AGS FEB Extraction Condition Change: The radial orbit in AGS has
   been changed to center in AGS, hoping to bring the actual tune
   closer to the set value. The position on the H10 flag is shifted to
   the left by about 5 mm (2 mm per small box on H10 flag). The H10
   strength should be increased accordingly to bring beam to proper
   position on UF1 flag. The expected change in beam momentum is
     Dp/p = -0.25 %
   i.e., the set gamma may need to be changed as
     Gamma = 12.1456 (old) ->  Gamma = 12.115 (newly guessed)
3. Sextant Power Supply: The ramp limit for the main sextant power
   supply is set (#9, p. 70) to be 3 Amp/sec. The proposed currents
   are:
     Dmain = 547 A
     Qmain = 494 A
     Qtrim = 0 A
4. RADON Application: Data taken for longitudinal emittance
   measurement through the AGS cycle.
5. Problems: 
   a) FEC138 had to be rebooted - may affect permit module & link.

================
JANUARY 25, 1997
================

Owl	TRBOJEVIC, Connolly, Tepikian, Mackay, Satogata, +1000s	#9 p72-78
--------------------------------------------------------
1) First beam from the AGS was obtained at 5 am
2) The BPMs did not work, FEC007 crashed three times.  The loss
   monitors at the beginning of the Y-line did not work.
3) After setting the design file we saw beam at both YF1 and YF2
   flags.  Set two trims upstream of the YF1 flag.
4) The loss monitors in the second part of the Y-line worked and
   showed losses at the end of the arc.
5) File saved Jan.25.9:30

Day	MACKAY, Peggs, Fischer, Tsoupas, Satogata, + 1000's	#9 p79-82
--------------------------------------------------
1) BPM timing readjusted by Todd and Tony -> Signals from u- and
   w-line
2) Loss Monitor Application problems -> often no values back,
   situation improved later, but no data from the beginning of the
   w-line
3) often no beam after request
4) fec007 had to be rebooted
4) magnet manager had to be restarted twice
5) the flag application occasionally stops fec007 from working
   properly thereby causing additional problems with current and loss
   monitors
6) wq6 current was still zero and disturbed the optics considerably
   (clearly visible on yf1)
7) last currents saved in Jan.25.97.15:20

Eve	WEI, Dell, Brown, (Tanaka, et al)			#9 p83-96
-----------------------------------------
1. Main Progress: The beam passed the y-line with almost no loss, 
   entered the sextant. Beam image seen on all u, w, and y line flags.
2. Tuning: With PS file    Jan.25.97.20:00    , the beam was tuned
   with about 100% transmission through current transformer yxf1. The
   beam was centered on flag yf2, passing through the Lamberson magnet
   with BLM showing loss at 3 meter after the Lamberson (ylm16.1).
   The switching magnet, yth7, and yth9 have been used for horizontal
   tuning, and ytv6 and ytv10 used for vertical tuning.
3. AGS Beam Conditioning: The AGS was tuned to lower bunch blowup near
   transition.
4. RHIC Data Archiving: Viewlog showing the sextant recooler
   temperature remainning at about 4.5K. All vacuum readings stable.
5. Problems: 
   a) Flag application stops if all 4 frame grabbers are used -- using
      2 instead.
   b) BPMs not working.
   c) MCR shows RHIC gates 5GE1, 5GI1 open, mostly due to system
      malfunction.  -- responsible person called in, and resweep.
   d) PS uarc4 WFG readback stops updating (magnet shown ON) -- target 
      desk called, and replaced analog card.
   e) Quench protection tripped for no obvious reason -- reset. ODH
      alarm still sounding, hopefully recover after sweeping.

================
JANUARY 26, 1997
================

Owl	SATOGATA, PEGGS, Thompson, Mane				#9 p98-114
---------------------------------------
1) At ~2000 (Jan 25) the 4 degree bend dropped.  Target desk replaced
   an analog card.  At 0100 (see item 2, below) we retuned with new
   calibration.  Restored the trims properly, and saved as
   Jan.26.97.05:30
2) At ~2130 (Jan 25) 2 gates at 4 o'clock showed open.  Learning curve
   problems with sweep procedure.  Original problem was a faulty
   microswitch.
3) Tune YTH5, YTH7, YTH9 to get beam HORIZONTALLY centered on YF1 and
   YF2.  Tuned YTV10 to get vertically centered on YF2.  BEWARE of
   maximum power supply strength of +/- 14 A (hence *3* horizontal
   trims).
4) Save Set   970126.0700   has beam centered on YF1 and YF2, H and V.
   This produces losses half way around the sextant!  First "beam" in
   RHIC?  Save Set   970126.0710   is a slight improvement.
5) Started tuning on loss monitors around the Lambertson.  Partially
   finished saveset, with YP1 amd YTV10 adjusted and intentional
   vertical offsets, saved as   970126.0800   

Day	FISCHER, Peggs, Tsoupas, Thompson			#9 p114-123
-----------------------------------------
Beam to sextant dump @ 14:09 !  970126.1530

Eve	WEI, Brown, Dell, Tanaka, (Satogata, et. al)		#9 p124-145
----------------------------------------------------
1. Beam parameter for sextant-dump hitting beam:
   The beam that hits the sextant dump with about 100% ATR-sextant
   transmission has the following parameter:
        Gamma = 12.15
        N     = 2 x 10^8 (up to)
        S     = 0.6 eV s/u  (95% bunch area)
        sigma(p) = 5 x 10^-4
        sigma(l) = 5.6 ns
        Ex    = 10.7 +/- 0.7 mm mr
        Ey    = 11.7 +/- 0.9 mm mr    (normalized emittance, 95%)
2. Momentum aperture scan:
   The full momentum aperture has been scanned by varying magnet
   strength
        Location               Dp/p (full)
        AGS                    1.0 %             (bumps on)
        U                      2.9 %             (4 and 8 degree bends)
        W                      1.2 %             (20 degree bend)
        SWM                    3.3 %             (switching magnet)
        Y                      1.5 %             (90 degree bend)
        Sextant entrance       3.4 %             (Lamberson)
3. Preliminary optics measurement:
   The beta function has been found to be very different from design,
   possibly due to matching problem.
    Flag          Measured beta(x,y)       Design beta(x,y)
    uf1           (192, 7)                 (66.0, 3.8)
    uf2           (38, 4)                  (6.4, 6.3)
    uf3           (19, 17)                 (14.4, 52.4)
    uf4           (38, 21)                 (39.2, 12.8)
    uf5           (15, 32)                 (12.7, 51.5)
    wf1           (90, 10)                 (65.0, 9.5)
    wf2           (5, 333)                 (6.0, 92.3)
    wf3           (134, 29)                (99.9, 8.7)
    yf1           (14, 305)                (19.8, 80)
    yf2           (29, 86)                 (14.1, 39.0)
    Note that yf1 is saturated even with maximum attenuation; others ok.
4. Emittance measurement:
   Using IPM in AGS, the horizontal emittance evaluated without taking
   into account of momentum spread is 14.6 mm mr. With coelascing, the
   momentum spread is large, and the contribution needs to be
   subtracted. Final value becomes for an intensity of up to 2x10^8
   per bunch is Ex = 10.7 +/- 0.7 mm mr, Ey = 11.7 +/- 0.9 mm mr
5. Difference orbits:
   BPM diffenence data is taken for u, w, and y lines by varying front
   trim (D(psuth2)=0.15 mr, D(psutv1)=-0.2mr), comparing with
   corresponding design values. The majority of u and w line BPM shows
   agreement. The y line data, however, indicates possible polarity
   reversal.
6. Problems:
   a) Permit link frequently trip;
   b) Front U line trims tripped, had to be set local at set value;
   c) sextant BPM not working, PS and Flag needs several restart;
   d) FEC018 rebooted.

================
JANUARY 27, 1997
================

Owl	SATOGATA, Thompson, Mane, Wei				#9 p145-153
-------------------------------------
1) At ~0000, Ganetis reported that permit link had dropped, along with
   main quad and dipole buses and switching magnet. Immediate solution
   was not available, an expert was called in, and systems were
   restored to 970126.1530 magnet settings and cautiously reramped by
   0230. George is officially requesting downtime on Monday to check
   out the main magnet systems.
2) As reported in last shift, psutv1 is having hardware problems and
   cannot be reset remotely. Attempts to leave it on but in local mode
   proved confusing, so it was turned off, and psutv4 was used to
   correct vertical injection orbit instead.
3) Losses appearing in middle of sextant eventually attributed to a
   small difference in the main dipole bus strength after midnight
   reset. (p. 149) Tweaking up this current restored full transmission
   through transformer yo4-xf3.
4) Sextant arc dipole correctors and loss monitors were used to
   clearly show 90-degree phase advance per cell in
   sextant. (pp. 151-152)
5) BPM timing in 1004A is very far off, o(10s of us), and remains
   uncorrected. Flash memory problem in 1004A BPM DSP confirmed by
   Chris Degen and Tom Shea, and newly burned DSP appears to work
   except for timing issues. BPMs up through lambertson region (1005E)
   are working, but appear to have polarity problems.

Day	MACKAY, Pilat, Tsoupas					#10 p1-4
------------------------------
1) Flag yo4-f3 recalibrated - shortly after it locked up.
2) Shutdown @ 2pm for tandem source change
	RF system test
	PSSWM needs to have klyxon changed
3) yxf1 not updating reliably.  Sometimes wxf1 does not update.
4) yo5-bh12 is wired up with +x pointing into the center of the ring.
   (AtR convention, not RHIC convention.)
5) RF can trip vacuum pumps when power is increased.  In steady state
   pumps might not trip.
6) Recommend not turning the PSSWM to "off", since this shuts off
   water flow.

Eve	KEWISCH, Ahrens, Fischer, Satogata			#10 p5-6
------------------------------------------
1) problems with power supplies througout the shift: utv1, swm and
   yarc90.  at the end of the shift utv1 is still not working. also,
   the slowClock task died 2x on fec009 and 1x on fec141. this caused
   the update on the screen to stop and complicated the diagnostics of
   the ps problems.
2) m. brennan used the shift to work on the multibunch
   synchro-extraction and was successful.
3) leif worked on the booster intensities (with no official result).

================
JANUARY 28, 1997
================

Owl	SATOGATA, Thompson            				#10 p7-19
--------------------------
1) Restored 100% transmission lattice for day shift, from total
   shutdown in evening shift. Former lattice (970127.0510) did not
   restore beam transport. New lattice created (970128.0645) with
   small changes in main arcs, vertical steering at injection, and
   vertical steering in lambertson region. There were few problems
   with power supplies this shift.
2) cfe-wh-inst (acnfec007) was rebooted; multipulse extraction of
   previous shift killed this front end when a flag profile monitor
   app was running, iconified, at the controls console. **>>Do not run
   flags with multiple extractions<<** acnfec131 was also rebooted
   because of this problem.
3) Early U-line magnet filter was cleaned and replaced by target desk,
   after reporting an 80-lb differential near 0200.
4) Typical beam currents, even after Brennan's efforts, were well
   below previous numbers, ranging from 1.0-1.6x10^8. Synchro
   extraction, reported to be tuned up last evening, did not work;
   approximately 40% of requests delivered beam.

Day	TRBOJEVIC, Pilat, Connolly				#10 p20-26
-----------------------------------
1) Measured the phase advance in the sextant: preliminary fit gives
   82.3 degrees for the 80 deg phase advance lattice.  We put 1 A kick
   in every horizontal corrector in the sextant (1 A = 0.00005994 rad)
   and measured the position on the yo4-f3 flag.  All flag and BCM
   data archived.  We repeated the measurement in the vertical plane,
   by varying the vertical dipole correctors. A more sophisticated fit
   is planned.
2) The main dipole quenched twice, misteriously. We ramped the main
   power supplies and the switching magnets back without problems.
   Carl Schultheiss moved the setpoint on the main dipole power supply
   by 0.85 A. The wfg setpoint that reproduces the same readings on
   yo4-f3 for y-dmain-ps is now 555.85
3) Roger took good data on the IPM during the main PS ramping.
4) Beam was turned over for RF tests at 1:30. That brought the vacuum
   valve down. It was not possible to run beam in parallel. They were
   asked to stop.  During the beam interruption utv1 was fixed.
5) fec009 had again a tSlowClk SUSPEND and it was reset (not
   rebooted).
6) When finally ready to get beam in the sextant again, no extraction
   from AGS. Kicker timing problem discovered. Beam turned over to AGS
   to reset kicker timing.

Eve	KEWISCH, Ahrens, Teoikian				#10 p27-35
---------------------------------
   Shiftgoal: Calibration of flags using the beam.
1) Measurements were done for uf3, uf4 and uf5. The measurements
   confirms the flag calibration within 10%.
2) The beam was moving from pulse to pulse horizontally.  The septum
   was was suspected as source of the motion. The spread of beam
   postions in ub5 was compared with the movement caused by a change
   of the septum setpoint. It was determined that a 0.25% change of
   the septum current produces the observed spred of the injection
   position.

================
JANUARY 29, 1997
================

Owl	WEI, Brown, Dell, (Peggs, Satogata)			#10 p36-60
-------------------------------------------
1. Sextant Aperture Scan: The sextant momentum aperture is scanned
   with fixed injection condition and the Lamberson, varying main
   dipole and quad strength. The aperture is
      Dp/p = 1.8 %
   The window for main dipole and quad is:
      Main D         Center          Window
      Dipole         554 A           549 - 559 A
      Quad           485 A           470 - 500 A
   for a beam of Gamma = 12.25.
2. Sextant Main Dipole/Quad Hysteresis Study: The hysteresis of the
   main dipole and quads are studied independently, recording all
   current transformer, and flag data of yf1 and yo4-f3. The lag in
   main dipole current is about 2 A.
3. ATR Injection Retune: The H10 is retuned to center beam on flag
   uf1. The 4 degree arc (psarc4) is rescanned, and the new set
   current is 20 A higher than the previous day. The new PS file is
       970129.08:00
4. Transverse and Longitudinal Emittance:
   With a gamma_T jump in AGS, the beam profile is greatly improved.
       S = 0.6 eV s/u  @   ~ 2.3 x 10^8 per bunch
       E_x ~ E_y ~ 11 mm mr
   A slight growth in vertical emittance is observed at AGS transition.
5. Viewlog RHIC Archive: -- show crate temperature at FEC007 and
   013 higher that 55 C. Vacuum condition change recorded during rf
   system development
6. Problems:
   a) suspected calibration problem in psarc4;
   b) utv1 works in local only.

Day	TRBOJEVIC, Connolly, Pilat				#10 p61-69
----------------------------------

1) The first hour and a half we repeated the phase measurements in the
   sextant - vertical tunes (Fulvia and Roger)
2) There was an access from 1000 - 1400
3) We came back at 1600 with all power supplies up.  There was a
   slight change in the AGS kicker strength to adjust the UF1 position
   of the beam.

Eve	KEWISCH, Ahrens, Tepikian				#10 p70-76
---------------------------------
shift goals:
	kicker timing
	flag calibration
	sextant phase advance
1) Kicker timing studies required no change in the u-w-y lines.
   Started measuring the beam in the sextant.  failure of power
   sub-station killed u-line until 10:30.
2) After restoring the beam flag calibration of wf1-wf3, calibration
   seems to be within 10% of expectation.  detailed number crunching
   postponed until tomorrow.

================
JANUARY 30, 1997
================

Owl	WEI, Brown, Dell, (Ahrens, Satogata)			#10 p77-94
--------------------------------------------
1. Sextant and ATR Dispersion Measurement: The dispersion in the
   sextant and ATR is measured by changing the radial loop function,
   while measuring and archiving beam position on all the 11 flags and
   all available BPMs in the sextant and ATR, along with all current
   transformer data and AGS rf frequency at extraction.
2. BPM Study: Difference orbit, generated by varing the first H trim
   uth2 by 0.15mr, is compared with prediction. Agreement is obtained
   on most of the u and w line BPMs, plus a few in the y line and the
   sextant.
3. Viewlog RHIC Archiving: Viewlog recorded about 0.2 C temperature
   surge in all 5 yellow recoolers, around that time a quench
   protection was tripped. Crate temperature on FEC007 and FEC013,
   above 55 C in last few days, droped below 50C.
4. Problems:
   a) Quench permit link was tripped about 10 times, each time causing
      PS down at switching magnet -- software problem suspected.
      ADC card in 5 alcove b was replaced. Main sextant PS has to be
      ramped locally at 1 A/sec.
   b) utv1 still in local.

Day	TRBOJEVIC, Connolly, Pilat				#10 p95-109
---------------------------------
1. We measured the tunes in the 90 degree arc-y.; the data needs to be
   analyzed.
2. From 11:00 - 13:00 there were kicker commissioning studies. It was
   found that the 32 KV,  expected design voltage for the kicker, 
   replaced successfully the yo5-tv9 dipole at 30A.
3. With the radial loop "on" in the AGS, we started  chromaticity 
   measurements, but they were interrupted by TANDEM failure.

Eve    FISCHER, Tsoupas, Satogata                               #10 p110-113
---------------------------------
1. M. Brennan worked 2 hours work on rf.
2. L. Ahrens timed-in the AGS extraction kicker.  
3. Attempted  measuring the kicker rise time from Bldg. 1005e.
4. Competing users (AGS RF, RHIC RF, BPM, kickers) lead to too many
   used pulses, and increased the radiation level in tunnel.  Kicker
   measurement were given priority.
5. The foil in Tandem was changed to reduce intensity.
6. Power consumption reached limit and was reduced.
7. Finally, the kicker rise time (with 4 kickers) was to be  measured 
   during the owl shift.

================
JANUARY 31, 1997
================

Owl  WEI, Dell, Brown, (Satogata, Mane)				#10 p114-136
---------------------------------------
1. Sextant Chromaticity Measurement: Simultaneous BPM, Current
   transformer (yxf1 and yo4-xf3), and flag (yo4-f3) data is taken for
   chromaticity evaluation. On 5 different momentum orbits (obtained
   by varying AGS radial loop), each of the 16 horizontal sextant
   correctors is powered at a 1 Amp difference, while archiving BPM
   and flag beam position. Another synchro-mode scan, obtained by
   varying independently each of the 31 horizontal and vertical
   correctors, is archived for comparison.
2. Sextant and ATR Dispersion Measurement: First and second order
   dispersion can be obtained by data collected above.
3. Sextant Transfer Matrix and Difference Orbit: Numerious difference
   orbits can be created from the above data and compared with the
   model.
4. BPM Development: BPMs in both ATR and sextant have been shown to
   finally work properly, both with synchro mode and radial loop. The
   difference orbits obtained by varying uth2 and utv4 show agreements
   with the model within about 10% accuracy in u and w line, predicted
   oscillation down the y line 90 degree arc, and good stability in
   most of the sextant units.
5. Problems: 
a) Excessive power consumption has been reported, possibly due to
   testing of the cryo group (8.2 MW increased to 11.7 MW). Viewlog
   shows surge in ambient flow of helium, more than doubled from its
   normal value -- asked by MCR to cut down comsumption by 1MW.
b) Chipmunks in the beginning of the sextant were tripped many times
   during the chromaticity scan -- MCR was instructed by K. Reace to
   ignore the message.
c) Flag application frequently refuses to update, even when only 
   1 framegrabber is used. Sometimes, the image was not updated, but
   the time stamp did, a potential trap for innocent users.

Day	TRBOJEVIC, Connolly, Pilat				#10 p137-142
----------------------------------
1. Site power comsumption is 51.6 MW -  Cryo load has increased by 1.5 MW.
  a). Shut off "A" line.
  b). Used 4.6 sec repetition rate.
2. 1000 shot history.
3. Reduced BLM gain & scanned with yo4th4.
4. Scanned BLM HV.
5. RF x-ray measurements at Bldg. 1004A.
6. No summary included in data book.
----------------------------------------- 
Eve   FISCHER, Tsoupas, Satogata, Trbojevic			#10 p143-149
-------------------------------------------
1. Successful multibunch injection into RHIC using injection kickers.
2. Injection kickers were used throughout the whole shift without
   problems.
3. Risetime of injection kicker was measured without kicker A
   (weaker).
4. Emittance measurement: hor 10 um, ver 12 um.
5. Ongoing work on BPMs.

================
FEBRUARY 1, 1997
================

Owl   KEWISCH and Pilat						#10 p150-154
-----------------------
1. Shift goals:
   a. flatten orbit
   b. change sextant phase advance
   c. measure phase.
2. Results:
   a. BPMs worked initially, with lots of restarts, but then failed.
   b. Orbit flattening was aborted after three hours.
   c. Ramped qmain current from 485 to 505 amps in steps of 5 amps and
      corrected position of beam on flag yo4-f3 after each step,
   d. Measured phase advance using correctors and flags.  Quench after
      80% of measurement.

Day	SATOGATA, Thompson, [Ahrens]				#11 p 1-9
------------------------------------
1. MAGNETS: Main magnet still down from evening shift, with Ganetis
        and crew investigating. Discovered correlation between magnet
        quench trip problems and changes in power grid after HIP
        shutdown at midnight. (p. 4) Magnets return at 15:45 (with
        quench detector limit set to 650 Amps) and full transmission
        restored by 16:00. Lattice saved as-is at end of shift, with
        some correctors tweaked, as 970201.1650.
2. ORBIT/BPMS: Orbit manager recompiled and does not crash for 6
        hours, then crashes several times late in day. Procedure for
        restart entered in log book. Before main magnet was restored,
        U and W line studies performed with reliable BPMs. Clorb
        correction shown to work with *simulated* single dipole errors
        in morning; later used to correct U and W-line horizontal
        orbits from 10+ mm to 2-3 mm from zero orbit. Clorb procedure
        entered in log book. Sextant and late Y-line BPMs remain not
        working at end of shift.
3. AGS: Some problems due to studies, tandem problems, and
        shutdown. BTA quad QV9 tripped several times. Delivered
        intensities varied wildly, from 6x10^7 early in shift to
        well-tuned 2x10^8 extraction near end.
*) REQUESTS:
   1. Jim Rose would like 1/2 hour of four-bunch extraction sometime.
   2. George Ganetis will be coming in at 7 AM tomorrow, Sunday, to
      attach trim yo4-qtv6 to the valve box. Estimate 1-1.5 hour main
      mag downtime.

Eve  FISCHER, Wei, Tsoupas					#11 p10-18
--------------------------
1. Needed to trim whole line again, reached 95% transmission, saved as
   970201.2115
2. For 3 quadrupole strengths in sextant, all horizontal and vertical
   correctors moved one after the other by 1 A and observed position
   on at flag yo4-f3.

================
FEBRUARY 2, 1997
================

OWL  KEWISCH, Pilat						#11 p19-28
-------------------
1. Shift goals:
   a. measure phase advance,
   b. measure beam profiles with different qmain currents.
2. Summary
   a. acnfec007 was rebooted.
   b. Wolfram tested his injection program. It works but is not ready
      for public use.
   c. Phase advance measurement:
      i. movement of baseline orbit was observed,
     ii. time constant is minutes,
    iii. phase advance measurement was completed,
     iv. baseline orbit was measured after each step.
   d. Profile measurement was started but not completed.
   e. Foil change ended shift.

Day  SATOGATA and Thompson					#11 p29-39
--------------------------
1. Stability of beam at yo4-f3.
2. Checked loss monitor sensitivity.
3. Saved: 
      a). Magnet file 970202.1613,
      b). BLM    file 02FEB1612, &
      c). BPM    file 161408.
4. Massive BPM data saved in OrbitDisplay/orbits/Feb02Day.
5. Plotted dependence of BLM sensitivity on th12 deflection.
6. No summary included in data book.
--------------------------

Eve   TRBOJEVIC, Connolly, Tepikian, Wei			#11 p40-56
----------------------------------------
1.  Measured Beta_x and Phi_x from BPM difference orbits kicking the
    by;
      yo5-uth10, yo5-uth12, and yo5-uth14.
2.  Measured Beta_y and Phi_y from BPM difference orbits using:
      yo5-utv9, yo5-utv11, yo5-utv-13, and yo5-utv17.
3.  Measured the horizontal tune, using the BPM's and flag yo4-uf3, at
    different quad bus currents.
        (qf) trim    trim quad -20A, +35A, +15A, 0A
4.  Used the BMP's to measure successfully the dispersion function in
    the SEXTANT.
----------------------------------------
================
FEBRUARY 3.., 1997
================
 Documentation of paramenters and plots of results              #11 p57-98






E-Mail Address
peggs@bnl.gov