Schedule for the Week

ver 8/8/2022 pws

 

FY 2022

Weekly Schedule

Monthly Schedule

Long Term Schedule

Shutdown Schedule

FES Weekly Schedule

 

Reminders:

ALL WORK MUST BE APPROVED. NOTHING SHALL BE DONE WITHOUT REVIEW/APPROVAL, NO EXCEPTIONS.

JOB TIME ESTIMATES: Job requests should reflect realistic fallback times and must include any necessary development time.

Post work testing for Operation and closeout statements ARE REQUIRED FOR ALL WORK. 

 

Facility Status

 

SRF Test facilities

Standby

                                                                                                                  

EBIS

Shutdown

 

LINAC/BLIP

Running

 

Tandem

shutdown

 

Booster

Shutdown

 

NSRL

Shutdown

 

AGS, AtR

Shutdown

 

RHIC

Shutdown

 

“Useful” links

CATV display

Job Request System

NSRL Schedule

 

Back to top

 

Wednesday 8/10

Time

Activity

Personnel

0800

Sweep Booster

CAS/MCR

1600

lock 930UG, MMPS, D3&D6

CAS

1630

Booster to RA after lockout

MCR

 

Testing:

Booster qtrims

Booster BLW (dummy load)

NSRL Transport

 

Back to top

 

Monthly Schedules:

NOTE: ALL Areas except LINAC and BLIP are in shutdown mode

 

Maintenance

 

BLIP Running

 

NSRL Setup

 

NSRL Running w/LINAC

 

 

 

Aug 2022 (Runs Pending approval)

 

Sun

Mon

Tues

Weds

Thurs

Fri

Sat

 

1

End 117Mev Run

2

Begin 200MeV run

3

Booster Locked until noon

4

5

6

7

8

9

10

Booster Locked for testing all day

11

End BLIP Run

12

LINAC Access for test

13

14

15

Begin BLIP 117 run

16

17

End 117 Run

18

10am

200 MeV 2 hour HEBT test

19

Start BLIP 200 MeV run

20

21

22

 

 

23

24

25

26

27

28

29

30

End BLIP

run

LINAC/BLIP Studies (No Access)

31

 

 

Sept 2022:

 

Sun

Mon

Tues

Weds

Thurs

Fri

Sat

 

1

End BLIP

2

Start LINAC Shutdown

RF off

3

4

5

Mod 6 Vac work

Chipmunks

Water system maintenance

6

Power outage L1,2&3

7

8

9

Pump Down LINAC

10

11

12

ACS testing,

Limited Access

13

--------------

14

---------------

15

---------------

16

17

18

19

 

 

 

20

21

22

Complete RSC CL for RF testing

23

Restore LINAC systems

24

25

26

LINAC RF Conditioning, NA LZ1

27

28

29

30

 

 

October 2022:

 

Sun

Mon

Tues

Weds

Thurs

Fri

Sat

 

1

2

3

Booster/NSRL

check out

4

Booster Heat Run

5

6

7

8

9

10

11

12

Set up Booster/NSRL with beam

13

14

15

16

17

NSRL Running

18

19

20

21

22

23

24

25

26

Maintenance

0700-1200hrs

27

28

29

30

31

 

 

 

Back to top

 

Shutdown FY’22 schedules:­­

 

Shutdown

 

Startup

 

Setup with beam

 

 

                                                                                             2023

 

Apr

May

Jun      

Jul

Aug

Sept

Oct

Nov

Dec

Jan

Feb

RHIC

Apr18th

Feb 6th

AGS

Apr18th

Jan6th

 

Booster

NSRL Running

To July 1

 

Setup

Sept15

~Oct 15th: NSRL Running and setup with beams from Tandem

 

 

 

Tandem

 

TTB Tune

NSRL

 

9/22

Oct 17

LINAC

Run to 9/1 w/approval

 

9/22

 

EEBIS

 

 

Feb 1st

EBIS

 

Jul 1, begin remove and install EEBIS

BLIP

 

Sept 1

 

 

 

Long term schedule:

 

     There will then be a protracted shutdown period of approximately 10 months during which sPHENIX will get rolled into the 8:00 IR, run and map its magnetic field, complete the installation of the detector sub systems, and commission the whole detector prior to the start of the 2023 RH IC run.

     Budgets have been requested to support three 28 week Physics runs for FY 2023, 2024, and 2025, which is projected as the completion of the RHIC program

 

Back to top

 

 Ver Monday, August 08, 2022 PWS