RHIC Run-11 Setup Bumps on the Road §
WFG failed to ramp bo6-tv9 to its requested current. §
Micardo and SVD orbit correction did not work. §
BLM was unmasked during snake on setup, but probably unknown to MCR. As the snake current was brought on gradually, no quench happened. §
OptiCalc slow, it took 99% CPU time. §
Yellow injection kicker timing hardware issue. It took us three shifts to sort it out. §
BLM first turn trigger problem and log problem. §
L20 tripped many times. §
LINAC Mod8 problem from time to time. §
The orbit feedback target orbits does not include the snake bumps. §
LINAC mode8 problem continues §
111 bunch injection caused blue2 polarimeter Si 4 to have high leakage current. §
Main quad glitch on the ramp caused significant beam loss, sometimes beam abort.. §
Vacuum valves near polarimeters closed when switching target in yellow. §
A bad BPM (yo8-bh4) wrong polarity) was put back online which caused confusion. §
Orbit feedback defined its separation bumps but did not use design one. Fixed by Mei and Al. §
Upstream polarimeter (outside ring) do not work. §
When correctors did not start ramp when ramp started, operation failed to abort beam but rely on BLM pulling the permit. It does not work all the time. §
LINAC Mod8 is not available for seven hours. §
No rotator ramp handy. The one produced in-situ had wrong IP4 DX magnet setting which caused DX magnet quench. §
Tape sequencer is not working properly when dealing with two ramps. Copy stone does not work as expected. §
Collimators were at wrong settings, which caused beam dumps. §
Orbit feedback pushed vertical orbit off by 1.6mm which caused heavy losses at collimators and beam induced quench. Six hours recover time. §
Due to the bug in the RhicLossThreshold, it can save/change setting without warning. The BLM events were all masked and did not pull the permit for the ramp which caused beam induced quench. §
Vacuum vavles at polarimeters were closed during polarization measurements and dumped beam. §
corrector P/S problem in RHIC holds the operation off for eight hours. §
Start seen emittance growth in blue. §
AGS RF cavity water leak, need ring access. §
AGS warm snake power supply failures, five hours lost. §
RHIC blue dump kicker noise problem. §
RHIC blue dump kicker noise problem. §
RHIC blue dump kicker noise problem. §
RHIC blue dump kicker noise problem(was fixed at the end of day). §
RHIC cryo power distribution system failure. Lost 14 hours. §
RHIC PASS system communication problem. Lost 5 hours. §
RHIC LLRF problem. Lost 7 hours. §
RHIC LLRF problem affected rotator setup efficiency and beam intensity in RHIC (limited to less than 1.2*10^11). |